2
299678
Acme aerospace must build its X16 rocket in 120 days. With 75% of this time gone, 420 workers have completed only 3/5 of the project. By what percent must the number of workers increase for the rocket to be completed on time?
Here is the way of my calculation:
total units of work = 120 days x 420 = 50400 units of work
90 days (75% of 120days) with 420 completed 3/5, so
Let's put x = # of additional workers need
30 days x (420 + x) = 20160 units of work (2/5 x 50400)
x = 252
so (252/420)x100 = 60%
But the correct answer is 100%
Could you be able to correct the way of my calculation if you think I am wrong?
Here is the way of my calculation:
total units of work = 120 days x 420 = 50400 units of work
90 days (75% of 120days) with 420 completed 3/5, so
Let's put x = # of additional workers need
30 days x (420 + x) = 20160 units of work (2/5 x 50400)
x = 252
so (252/420)x100 = 60%
But the correct answer is 100%
Could you be able to correct the way of my calculation if you think I am wrong?