2
299678
that I don't understand the solution
Q1. . Two people can complete a job in 10 days. If one person tries to complete the job by taking a day rest after every 5 days a work. How many days will he complete> my calculation was 24 days, but the correct answer is 23 days
Q2. 6 men take 2 days to complete a work whereas 4 women take 4 days to complete the work. How men days will 3 men and 2 women working together take to complete the same work? correct answer is 8/3 days
Q1. . Two people can complete a job in 10 days. If one person tries to complete the job by taking a day rest after every 5 days a work. How many days will he complete> my calculation was 24 days, but the correct answer is 23 days
Q2. 6 men take 2 days to complete a work whereas 4 women take 4 days to complete the work. How men days will 3 men and 2 women working together take to complete the same work? correct answer is 8/3 days