R
Rook
Hey Guys,
I was hoping someone could help me figure this out:
Question:
A construction firm receives an important contract and
hires 15 temporary workers in addition to its full-time
staff. If the entire full-time staff of 25 could complete
the job in five months, and if temporary workers work
5/6 as fast as full-time workers, how much time will
be saved by hiring the additional workers?
I am not looking for an answer but more of an explanation of how to get to the answer. Thanks so much!!
I was hoping someone could help me figure this out:
Question:
A construction firm receives an important contract and
hires 15 temporary workers in addition to its full-time
staff. If the entire full-time staff of 25 could complete
the job in five months, and if temporary workers work
5/6 as fast as full-time workers, how much time will
be saved by hiring the additional workers?
I am not looking for an answer but more of an explanation of how to get to the answer. Thanks so much!!